On June 2, 2025, Houston City Council approved a $2,643,753.10 construction contract with Reliance Construction Services, L.P. for New Front Easement Reconnections as part of the Substitute Service Line Program (SSLP). The project will relocate sewer service lines for approximately 400 properties citywide, abandoning back-of-lot connections and installing new front-of-lot reconnections to existing wastewater mains. The contract duration is 730 calendar days, with a total project appropriation of $2,933,128 including contingencies, testing services, and CIP cost recovery. Testing services will be provided by Terracon Consultants, Inc. under an existing agreement. The contract complies with the City’s Pay or Play ordinance and fulfills M/WBE participation goals of 17% MBE and 7% WBE through local firms. No Hire Houston First designation was met.